Background
The project will replace an 8” metal roadway culvert and overland flow path behind residential properties with a new piped system in the street right-of-way and easement in a private driveway. We are fast tracking the project to minimize impacts residents are currently experiencing. We are
also teaming up with the County of Sacramento Department of Transportation on the design and funding of this project.
Project Description
The project will repair the existing system by installing new pipe, manholes, and inlets (see attached newsletter map). We estimate construction will take four weeks with work hours of 8am-3:30pm. The contractor will stage equipment on Landis Avenue and the private driveway during the day. Residents should expect construction noise and traffic impacts during the project.
Quality Control
County Construction Management and Inspection Division will manage the field work and inspections for the project. David Phillips will be the construction inspector. He will resolve most field issues and ensure the work meets the design plans and specifications. Eyad Almasri will be the Resident Engineer overseeing construction and handling major field issues.
Project Location Map

Project Schedule
Begin construction – April 7, 2025
End construction – May 2, 2025
All dates are tentative and subject to change.
For More Information,
Please Contact:
David Bolen
Project Engineer
(916) 874-8645
Eyad Almasri
County Construction Management
(916) 879-3612
Marcus Gumm
Contractor,
North Star, (530) 682-3951