Zone 11 Credit Schedule

Appendix 2

Storm Drain Pipe [1]

Schedule DEffective March 22, 2026
12"$94.97 /LF
15"$106.00 /LF
18"$122.03 /LF
21"$138.97 /LF
24"$152.31 /LF
27"$176.59 /LF
30"$181.78 /LF
33"$213.52 /LF
36"$222.35 /LF
42"$304.35 /LF
48"$350.36 /LF
54"$372.00 /LF
60"$414.59 /LF
66"$528.35 /LF
72"$611.60 /LF
84"$611.60 /LF
96"$611.60 /LF

Manhole Size [2]

Schedule DEffective March 22, 2026
48"$8,974.88 /EA
60"$13,059.92 /EA
72"$16,116.25 /EA
84"$18,818.39 /EA
96"$23,161.10 /EA
108"$24,671.83 /EA
Saddle Manhole$11,580.53 /EA
4" thick Concrete Channel Lining$15.00 /SF

 

Fencing and Gates

Schedule DEffective March 22, 2026
3' high post + cable$33.47 /LF
Pipe gate $6,500.00 /EA
6' high wrought iron with gates$65.18 /LF
6' chain link fence with gates$39.47 /LF
4' chain link fence with gates$36.47/LF

 

Miscellaneous

Schedule DEffective March 22, 2026
Signs 16sf or smaller$730.55 /EA
Signs >16sf$1,095.85 /EA
Miscellaneous metal (handrails, headwall racks, and flap gates) $14.77 /LB
Channel excavation [3]$8.00/CY
Fine grading channel/basin bottom and sides$0.00 /SF
Basin excavation [3] $7.50 /CY

Erosion Control Riprap [4]

Schedule DEffective March 22, 2026
Class 1 backing rock$108.57 /ton
Class 2 backing rock$115.79 /ton
1/4 ton$126.66 /ton
Cobbles$115.79 /ton
GeoWeb - rock weir$113.24 /ton

Access and Maintenance Roads

Schedule DEffective March 22, 2026
1" thick asph conc$1.00 /SF
1" thick aggr base$0.60 /SF
1" thick Decomposed Granite $0.70 /SF
Geotextile fabric$0.50 /SF

Repair Surfaces

Schedule DEffective March 22, 2026
Asphalt concrete patch paving$18.00 /SF
Hydroseed$5,000.00 /acre

Miscellaneous Concrete [5]

Schedule DEffective March 22, 2026
Junction Box$3,021.77 /CY
Headwall$3,021.77 /CY
Stairway$3,021.77 /CY
Flat pad$1,809.44 /CY
Ramp$1,809.44 /CY
Driveway$1,809.44 /CY
Weir Structure$1,809.44 /CY

Notes

[1] Smaller pipe sizes are often used for basin outlets 

[2] Manhole unit price is complete including rim and lid

[3] Same unit price regardless of method of transport 

[4] Riprap class is based on Caltrans Specifications

[5] Concrete unit price includes rebar, structure excavation and backfill, sub-base material and grading